Project Progress Status

April 2024 Overall Progress

96.32%
Lot 1 Progress As of April 2024 - ( 96.25% )
Lot 2 Progress As of April 2024 - (96.37% )

March 2024 Overall Progress

95.95%
Lot 1 Progress As of March 2024 - ( 95.55% )
Lot 2 Progress As of March 2024 - (96.25% )

February 2024 Overall Progress

94.5%
Lot 1 Progress As of February 2024 - ( 92..68% )
Lot 2 Progress As of February 2024 - (95.90% )

January 2024 Overall Progress

93.98%
Lot 1 Progress As of January 2024 - ( 91.69% )
Lot 2 Progress As of January 2024 - (95.74% )

December 2023 Overall Progress

93.58%
Lot 1 Progress As of December 2023 - ( 91.05% )
Lot 2 Progress As of December 2023 - (95.52% )

November 2023 Overall Progress

93.02%
Lot 1 Progress As of November 2023 - ( 90.08% )
Lot 2 Progress As of November 2023 - (95.27% )

October 2023 Overall Progress

92.56%
Lot 1 Progress As of October 2023 - ( 89.43% )
Lot 2 Progress As of October 2023 - (94.97% )

September 2023 Overall Progress

91%
Lot 1 Progress As of September 2023 - ( 88.80% )
Lot 2 Progress As of September 2023 - (94.73% )
Lot-1 Progress
Lot-2 Progress

August 2023 Overall Progress

89%
Lot 1 Progress As of August 2023 - ( 87% )
Lot 2 Progress As of August 2023 - (93% )
Physical Progress Lot-1
Physical Progress Lot-2

July 2023 Overall Progress

88%
Lot 1 Progress As of July 2023 - ( 83.53% )
Lot 2 Progress As of July 2023 - (92.397% )

    
Bridge & Culverts
99.27%
    
Station & Buildings
47.79%
 
Signal & Telecom
35.00%

    
Earthworks
94.94%
    
Track
73.81%

    
Bridge & Culverts
99.70%
   
Station & Buildings
83.399%

    
Earthworks
98.31%
    
Track
86.329%

Lot 1 Progress July 2023
Lot 2 Progress July 2023
DCRP Monthly Progress June 2023
May MP Update
April 2023 Mothly Progress
March-2023-Progress-2
February-2023-Progress-2
January-2023-Progress

Our Location

Thumb Gallery

error: Content is protected !!