Trial Run Train

15 October Trial Run has been postponed and new date will coming soon.

Sources of the Dohazari-Cox’s Bazar rail project said that although it was launched on November 12, the train service for tourists will start at the end of November. As some bridges including Kalurghat are weak, trains will run there with reduced speed. The train will run at a speed of 100 km for the rest of the way.

The authorities have postponed the experimental train movement from Chittagong’s Dohazari to Cox’s Bazar.

The train was scheduled to depart from Dohazari on Cox’s Bazar railway on Sunday.
Director of Dohazari-Cox’s Bazar Rail Project. Subaktgin confirmed this information around 11 o’clock on Friday.

He said that the experimental trial is not possible with the six coaches that have been brought to Patia from Dohazari to Cox’s Bazar. Apart from that, it will take time from 20th to 21st for Kalurghat Bridge to be fully ready. The new compartment will arrive before that date. Maybe the test journey can be started at that time.’

He also said that on October 15, Railway Minister Nurul Islam Sujan will inspect the entire railway from Dohazari to Cox’s Bazar. At that time, a full decision will be made on various issues including the inauguration on November 12.

Sources of the Dohazari-Cox’s Bazar rail project said that although it was launched on November 12, the train service for tourists will start at the end of November. As some bridges including Kalurghat are weak, trains will run there with reduced speed. The train will run at a speed of 100 km for the rest of the way.

New Source : News Bangla 24.com