86.98%
Lot 1 Progress As of June 2023 - ( 81.31% )
Lot 2 Progress As of June 2023 - (91.330% )
Bridge & Culverts
99.06%
Station & Buildings
46.79%
Signal & Telecom
33.00%
Earthworks
91.30%
Track
70.87%
Bridge & Culverts
99.60%
Station & Buildings
78.732%
Earthworks
98.16%
Track
85.983%